Time Performance of Construction Arbitration

Lead author · Corresponding
Oshin Suryawanshi
Graduate from Amity Law School, Noida, India
Abstract

One of the main concerns among disputants in arbitration is that the duration is taken to resolve their disputes. Although it’s has been suggested that sole arbitrators and multi-member tribunals should conclude arbitration cases within 3 and 6 months, respectively, it remains unclear why some disputes take longer than others to resolve. The importance of timely resolution of construction disputes can’t be exaggerated. Studies have established resolution time as one of the essential considerations in selecting dispute resolution methods. Conflicts that take an extended time to resolve essentially fracture business relationships escalate construction costs, delay projects, cause emotional stress, and damage reputation, reducing business turnover.

Type
Research Paper
Information
International Journal of Legal Science and Innovation, Volume 3, Issue 4, Page 280 - 284
Creative Commons
CC BY-NC 4.0 This is an Open Access article distributed under the terms of the Creative Commons Attribution–NonCommercial 4.0 International (CC BY-NC 4.0) (https://creativecommons.org/licenses/by-nc/4.0/), which permits remixing, adapting, and building upon the work for non-commercial use, provided the original work is properly cited.
Copyright
Copyright © IJLSI 2026
Disclaimer
The views and opinions expressed in this manuscript are those of the author(s) alone and do not reflect the views, policies, or position of the Journal.

Export citation


        
📢 Call for Papers — Volume VII - Issue V now open  ·  Impact Factor 6.285  ·  Indexed in Manupatra, ROAD & Google Scholar Submit Now →
Chat with us